January 2014
June 2016
- 1,271 towers installed - including 1,001 guyed structures & 270 self-supporting structures
- 3,211,022 bolts were used to install 11,896 metric tons of steel
- Crews installed 2,081 foundations and 4,364 anchors
- The total length of conductor installed was 6,296.7 km
- There were 889 staff working on the project for a total of 1,155,452 labour hours